Sky Signage Export Project – Deloitte Terrace Installation by AD World Signages
Project Overview:
Project Name: Deloitte Terrace Signage Installation Location: EcoWorld 4D, Bellandur, Bengaluru Client: Deloitte Executed By: AD World Signages Pvt. Ltd. Collaborators: JLL & Deloitte Project Teams
AD World Signages was entrusted with the prestigious task of installing the Deloitte brand signage at EcoWorld 4D, Bengaluru—a key sky signage export-level project. The execution required high-altitude expertise, precision engineering, and a strong focus on safety. This project is a testament to our ability to deliver export-quality sky signage solutions at national and international standards.
Scope of Work – Sky Signage Installation
Detailed site analysis and planning
Safety protocol formulation and execution
Structural steel fabrication and erection
Signage fabrication and installation
Electrical wiring and panel setup
Surface painting and post-installation cleanup
The comprehensive scope included everything from initial assessment to final handover—executed seamlessly under stringent safety and quality parameters.
Site visit & Planning for Safe work Execution with JLL team.
Joint inspections with JLL Safety and AD World Safety Team.
Preparation of Standard Operating Procedures (SOPs)
Scaffolding and lifeline layout planning
Mock ups for ingress points
Safety planning was at the heart of this project. From the beginning, we worked closely with JLL teams to ensure all safety measures were properly outlined and approved.
SOP as per planning & discussing with JLL Safety team.
Drilling anchor bolts into terrace structure
Fixing life-line ropes and harness points
Ensuring team members followed PPE protocols
Installation of man-catching safety nets
Every team member underwent safety briefing and was fully equipped with high-grade PPEs. We installed life-lines and anchor points before initiating the elevation work.
Drilling anchor bolts to install life-line rope.
Harness Hooked to the existing anchors and Drilling safely.
After Installation of Life-line as per SOP.
Scaffolding, Net, Ingress & Egress installation as per SOP.
Customized scaffolding to fit terrace conditions
Interlocking scaffolds with the parapet wall
Access/egress pathways marked clearly
Secure scaffolding was essential for work at such heights. We implemented controlled ingress/egress paths in accordance with SOPs.
Posters for safety awareness & PPE.
Safety posters and instruction boards at site
Daily toolbox talks and worker briefings
PPE reminders and visual cues for safety
Creating awareness was as important as implementing safety. Our daily briefings and constant monitoring ensured 100% compliance throughout.
Scaffolding shifting & MS material cutting, shifting to terrace.
Material transfer through service lifts
Floor protection ensured during shifting
MS materials cut precisely as per structural requirements
All materials were handled with care to prevent damage to the building interiors and ensure efficient installation on-site.
Drilling Nut-Bolts & fixing with bolt Solution & fixing baseplates.
Precision drilling for anchor points
Use of bolt solution to ensure grip
Alignment of baseplates with laser markers
Accurate baseplate positioning laid the foundation for safe and sturdy structural fabrication.
MS tubes cutting and structure & frame fabrication & erection.
On-site tube cutting and welding
Fire blankets used to avoid floor damage
Structure erected with alignment tools and PPE usage
Each structural element was fabricated and assembled on-site, ensuring full alignment and adherence to safety standards.
Double coat primer & Silver grey painting.
Anti-rust primer applied in two coats
Aesthetic topcoat in silver grey for longevity and brand consistency
Our paint application not only met aesthetic standards but also ensured long-term durability against weather exposure.
Signage back & front Letter installation.
Mounting of individual channel letters from the rear
Secure fixing using industrial-grade bolts and screws
Alignment checks conducted post-installation
The signage was installed letter by letter, carefully aligned and securely fastened to the structural base.
Electrical connection, DB & tray installation.
Internal wiring for LED lighting
DB board and cable tray setup
Final testing of illumination and control systems
The electrical system was integrated to ensure optimal night-time visibility while maintaining safety standards.
Signage Letters Touch-up & final painting.
Letter alignment verified with visual and laser tools
Minor paint touch-ups done for a flawless finish
We conducted a final inspection for aesthetics and functionality before concluding the installation process.
Removing scaffolding, Man-catching Net & Lifeline rope.
Safe dismantling of scaffolding and safety nets
Controlled lowering of tools and equipment using rope methods
Post-work cleaning to leave no debris or damage
We ensured the site was returned in pristine condition post-installation, with zero damage and full client satisfaction.
Housekeeping and Final picture of site.
Final pictures of Signage.
Final walkthrough with JLL and client
Hand-over with installation and safety report
Zero accident achievement
Special thanks to Deloitte and JLL Safety Teams
The project was a success story of collaboration, commitment, and adherence to safety—delivered on time and with zero incidents.